Skip to content
Dismantling, Shifting, Re-installation, Testing & Commissioning Of Chiller At Execujet Facility
LOCATIONDUBAIYEAR2022CONTRACTORSOUTH ENERGY DWC-LLCCONTRACT VALUEAED 2,000,000.00ACTIVITIESElectrical Works, Chillers Disconnecting, Shifting, Re-Installation, Testing & Commissioning of Chiller plant at Execujet MRO + FBOShare
SCOPE OF WORKS
- Supply & Installation of Air Separator-01 nos
- Supply & Installation of Expansion Tank, with make-up system-01 nos (pressurization unit)
- Supply & Installation of domestic water connection with Flow meter and chamber
- Supply & Installation of Water Tank
- Fire safety as per civil defence requirement
- Supply and installation of 1no manual chemical dosing pot with 1st charge of chemicals
- Supply and installation Obtaining DEWA Construction Supply & installation of earthing system for the MDB