LOCATIONDUBAI – UNITED ARAB EMIRATESYEAR2016CONTRACTORAuthor naSTEEL CONSTRUCTION ENGINEERING CO. LLCmeCONTRACT VALUEAED 3,400,000.00ACTIVITIESUnderground Pre-Insulated Chilled Water Network Pipe Works Phase 01 DCP & Re Routing of Underground Chilled Water Network Pipe WorksShare
SCOPE OF WORKS
Laying of pipes and fittings.
Installation, welding and testing of underground pre-insulated pipes and fittings.
Installation of all free issued BFV, GV, AAV and Fittings as per provided drawings.
100% UT for all welded joints.
Hydro Testing of Chilled water supply/return piping.
Joints painting.
Installation of insulation kits for all joints.
Rubber insulation & cladding for the pipe, fitting & valve inside valve chamber.