LOCATIONDUBAIYEAR2022CONTRACTORSOUTH ENERGY DWC-LLCCONTRACT VALUEAED 2,000,000.00ACTIVITIESElectrical Works, Chillers Disconnecting, Shifting, Re-Installation, Testing & Commissioning of Chiller plant at Execujet MRO + FBOShare

SCOPE OF WORKS  

  • Supply & Installation of Air Separator-01 nos 
  • Supply & Installation of Expansion Tank, with make-up system-01 nos (pressurization unit) 
  • Supply & Installation of domestic water connection with Flow meter and chamber 
  • Supply & Installation of Water Tank 
  • Fire safety as per civil defence requirement 
  • Supply and installation of 1no manual chemical dosing pot with 1st charge of chemicals 
  • Supply and installation Obtaining DEWA Construction Supply & installation of earthing system for the MDB